The main building construction of Senior Material Europe’s Phase II project has been completed on schedule, marking a significant “milestone” in our project development. This achievement lays a solid foundation for the successful installation of equipment and facilities moving forward!
With the collaborative efforts of dozens of construction partners and hundreds of dedicated builders, after 11 months of hard work, Senior Material Europe AB successfully completed the main building and ground infrastructure for the Phase II factory on October 31, 2024. The project was designed and scrutinized by Swedish professional design teams in compliance with Swedish building regulations, with Senior Material Europe AB overseeing the project’s regulatory approvals and ensuring construction met stringent safety, environmental, and quality standards.
Throughout the Phase II construction process, we received robust support from our global partners, valuable supervision and guidance from various governmental authorities in Sweden and Eskilstuna, and strong encouragement and recognition from multiple battery clients across Europe. This success is a testament to the teamwork, high efficiency, and “new speed” of Senior’s international project execution, showcasing Senior Material Europe AB’s exceptional project management capabilities.
Key Milestones of the Project:
- November 21, 2023: The Phase II project officially broke ground in Eskilstuna, Sweden.
- April 16, 2024: The first concrete foundation for the main building was poured, marking the rapid progress phase of the main construction.
- May 17, 2024: Installation of the first steel column in the main building, signifying the start of structural construction.
- October 31, 2024: Completion of the main building and ground infrastructure for the Phase II project as scheduled.
Attached: Selected images from the Phase II project site on October 31.